The Board would like to share a few updates regarding the 860 & 870 lobby renovations:
860:
• Renovation work will start in the 860 lobby on Monday Feb 2nd.
• The first steps will be prep work, e.g. protecting the marble and installing dust protection.
• Next steps will include taking down the ceiling and wall moldings, followed by installing Sheetrock lamination on the ceiling and skim coating the walls.
• There will be access at all times except when the contractor’s crew is doing any vestibule work. We will pass along more information about that as we have specifics to share.
870:
• Tile work on the main lobby floor is expected to be completed by Monday Feb 2 and the vestibule floor is expected to be completed by Tuesday Feb 3.
• The 1st floor corridor’s walls and ceiling have been painted. The doors, lobby walls and vestibule will be painted next week.
• Marble cleaning is scheduled for Feb 9, and will take 7-10 days to complete.
• After the marble cleaning is complete, the painted surfaces will be touched up and new lighting fixtures installed.
As always, if you have any questions about the renovations, please contact our Managing Agent Howard Landman at 212-483-0700 or hlandman@sirenmgt.com.