The Board would like to share an update from our contractor, L&Z, regarding the Local Law 11 work currently ongoing at West Gate House. This is the facade safety inspection project that requires scaffolding/sidewalk sheds installed around the building.
The current projections show that the work for 860 should complete in early October. The 860 sidewalk shed is targeted for removal during the week of October 8. The installation of the 870 sidewalk shed is scheduled for the week prior (during the week of October 1) so that the work crew can transition from 860 to 870 with minimal downtime.
These target dates are subject to change as they can be impacted by weather or other unanticipated issues.